AAMC Data Center Renovation

Washington, DC

aamc_dc_01 aamc_dc_02 aamc_dc_03

Complete Commissioning, Inc. was contracted by the owner (American Association of Medical Colleges) to perform Design Phase and Construction Phase commissioning for renovations to the existing critical environment data center for AAMC..

Systems Commissioned Include:

  • Air Cooled Chillers
  • Chilled Water Piping Systems
  • Blended Chilled Water Pumping Systems
  • High Density In-Rack Coolers
  • Building Automation Systems
  • Underfloor Leak Detection Systems
  • Humidifier Systems and Controls
  • Vibration Isolation
  • Test and Balance
  • AC Motors and Drives
  • Exterior Lighting Systems
  • Uninteruptible Power Systems (UPS)
  • Transformers
  • Electrical Panelboards
  • Electrical Switchgear
  • Emergency Generator
  • Grounding Systems